Project:
 Development of Astrakhanskaya GRES with mounting PGU-110


Country:  Russia
City / region:  Astrakhan
Client:  South Generating Company YuGK-8 (after reorganization - LUKOIL-Astrakhanenergo)
Financing agency:  YuGK-8 (LUKOIL-Astrakhanenergo)
Project costs:  RUR 5.6 bln
Project period:  2008-2011

Short description of project:
 

Reconstruction of the Astrakhan GRES with the construction of PGU-110 "turn key" with a maximum electrical output (net) of at least 110 MW and a maximum thermal capacity of not less than 182 Gcal / hour.


Services:
 

From July 2008 to April 2011 ZAO "Geningconsult" rendered services as the Technical Agent for the monitoring of the "turnkey" contract for construction of PGU-110 , implemented by ZAO "Energokaskad".

The composition of
services included:

- Monitoring of the Contractor schedules;
- Control the use of funds;
- Spot checks of executive and operational documentation;
- Control of start-up;
- Control to ensure timely funding of construction;
- Issuance of the Board of Directors explanations and conclusions in the course of the Project;
- Monitoring for changes in work performed;
- Work on the operational headquarters for the construction and commissions on acceptance of completed construction;
- Preparation of reports.